ECM has a track record of versatility and successful project and maintenance work. Here are few examples
Mermaid Marine Dampier Supply Base Expansion 2001/2002
ECM was appointed overall project manager of the $26m expansion
which included a 4000t slipway, dredging works involving 750,000
m3 of dredging, design and construction of heavy load out
wharf, quarrying, land reclamation and revetment work, installation
of potable and fire water storage, pumping and distribution
pipe work, storm drainage, pipeline spooling area. An idea
of the scope of this work can be found on Mermaid Marine's
website which is at www.mermaidmarine.com.au
Hanjin Dampier Salvage , 2002 (300,000t
ore carrier)
In September 2002 the Hanjin Dampier ran aground in the shipping
channel in Dampier. The vessel was refloated under the direction
of the salvage company by transferring approximately 5000t
of cargo using a 300 tonne capacity crane onto waiting barges,
for transfer to shore.
Working with Mermaid Marine, ECM provided the services for
the coordination of engineering activities including the stability
and structural analyses, performing the rigging study, providing
mobilisation services to the barges, and supply of manpower
and logistical services involving the transfer of cargo from
vessel to barge to shore.
Karratha Back Beach Boat Ramp, 2002 (Shire Of Roebourne)
ECM successfully tendered for and constructed the boat ramp and jetty.
This entailed the demolition of the old boat ramp, earthworks, supply and installation of precast concrete panels, jetty fabrication and installation. Work was required to be completed within tidal windows.
Burrup Desalination Plant Supply of Inspection Services, 2003/04 (Watercorp)
ECM tendered for the supply of construction project management services to the Watercorp and provided a civil inspector for the duration of the civil work.
Cape Lambert Dust Suppression Pipe work,
2004 Rio Tinto (SKM)
Engaged under contract to Rio Tinto with SKM as project managers,
ECM was contracted to supply additional dust suppression capability
to the iron ore stock piles at Cape Lambert Western Australia.
This involved the supply and installation of several kilometers
of dust suppression systems including the installation of
HDPE and galvanized steel piping, thrust blocks and water
cannons. This contract was completed on budget and ahead of
program.
East Spar Equipment Building Extension, 2004 (Apache Energy)
Contracted to Apache Energy, ECM was engaged to extend the
existing building as part of an expansion underway on Varanus
Island, off the coast of Western Australia. This work included
the supply and installation of rock anchors, pre cast concrete
footings, structural steel, cladding and other building elements
within an operating gas plant. The quarantine and logistical
issues required a high degree of planning and coordination.
Cockatoo Island Ship loader and Wharf
Engineering Assessment, 2003/04
(Cockatoo Iron JV)
ECM was engaged to do a preliminary engineering assessment
with the view to ongoing inspection and repair work. ECM was
subsequently required to design and install a steel fuel pipeline
from the wharf dolphin back to shore. On-going inspection
and maintenance work is pending. Restricted access along the
wharf required the design and use of a specific access system
and careful design of the pipeline supports and the route.
Cockatoo Island is located at the northern end of the Kimberleys
in Western Australia. Access to the island is by barge or
light aircraft.
Sinker Pipeline and Dredger Maintenance,
2004 (Ballast Ham Dredging)
In Dampier, Western Australia, ECM constructed approximately
1.5 km of 800mm diameter pipeline which was progressively
pushed offshore before being sunk and connected to the offshore
dredge. ECM was also engaged for the provision of boilermaking
and welding services on the dredge and other plant for the
duration of the contract.
Plough Barge Mobilisation, 2004 (Boskalis
Australia)
ECM was engaged by Boskalis Australia to assist with the detail
design, fabrication and assembly of barge deck assemblies
for their contract for dredging work at Dampier Port. This
work involved the design and fabrication of pushing frames,
support beams, and deck connections, and included final assembly
and installation.
Marine Construction Mobilisations and
Vessel Repairs, Dampier, Western Australia
Owing to on-site welding and boilermaking resources which
are resident in Dampier, ECM has been involved in a great
number of vessel repairs, mobilisations and demobilisations.
This work involves the supply of welding and boilermaking
services for the sea fastening of various offshore construction
kit and other structures, as well as vessel repairs and minor
modifications. Clients have included, Technip, Subsea 7, Clough,
Apache Energy, Icon Engineering and vessel operators Farstad,
Adsteam, and Mermaid Marine.
Wharf and Navaid Repair and Maintenance Work
ECM has a track record of repairs, modifications and maintenance
work to a variety of offshore structures including wharves,
channel markers and platforms. ECM has used other vessel
operators and professional diving companies on occasions for
this work. EMC has as part of its own kit, purpose-designed
and -constructed access equipment and lightweight welding
and power sources.
FW Heavy Lifts 2006/07
The construction of Phase 5 of the Woodside gas plant on the Burrup Peninsula in Western Australia was achieved using a module approach to assemble the plant. In the course of this work ECM were engaged to take care of the seven modules that needed to be placed onto the LNG wharf. This was different to the rest of the modules were essentially roll on roll off.
The seven modules comprised of 4 loading arms of 75 T each and three process modules at varying weights between 120T and 105 T.
These modules had to be loaded back on a barge using a Manitowoc 2250, the barge transported to the new LNG wharf, connected to a specifically designed mooring system, before being winched alongside(but not contacting), a jack up barge mounted Favco 1500 Crane for loading onto the jetty.
ECM were responsible for
- Preparation of procedures
- Lift studies for loading onto the barge
- Lift studies for loading onto the jetty
- Installation of Barge mooring gear including procurement,
- Barge deck layout, positioning of the jack up barge, provision of attendant vessels
- Provision of all labour, supervision and engineering
- Design and installation of mooring system. ( ably supported by International Maritime Consultants, Fremantle)
- Barge, Vessel and Lift supervision
The job went to schedule and without incident. Client references include Neil Waddington, Project Engineer Foster Wheeler , Tel 08 9186 6374.
East Intercourse Island Fender Deluge System :Riotinto 2006/07
The East Intercourse Island Iron Ore facility in Dampier Western Australia belongs to Pilbara Iron. After vessel are loaded with iron ore they are some times moved along the wharf into a layby berth. This activity requires a water spray over the fenders to reduce the friction between the vessel and the fenders.
ECM were requested to develop a spray system utilizing two 30KW pumps.
The solution ECM cam up with required an installation that allowed each individual pump to be able to slide down a rail , with later withdrawal being made possible by use of an overhead monorail system that enabled the pump to be lowered into a waiting vessel.
The dual pump system enabled alternate switching. Sea water was then piped to each of the 9 spray nozzles located along the wharf.
The solution involved a purpose designed clip on structure that was erected by barge as it was not possible to cranes onto the wharf structure.
ECM were responsible for
- Concept development
- Detail Engineering
- Fabrication
- Installation
- Electrical work
- Piping
- Commissioning
- preparation of operations and maintenance manuals
reference client contact ; Julian Carr-White Tel 0408 917 530, 08 9143 5709
|